Contract Risk—Four Things You Can Do to Mitigate It
by Doug Reitz, Maxim Consulting Group
Over the years, I have seen skilled subcontractors do outstanding work and then not get paid for it. It could be disputes that drag on for months, unforeseen delays, missed contractual deadlines or even a misunderstanding that escalated. For some owners and GCs, holding payment is the quickest and easiest way to get a trade contractor’s attention or to even hold it ransom to get what they want in a dispute. Mitigating risk starts with the contract; knowing what is in it and being able to comply if challenges arise.
There are four key areas that affect risk and payment that you have little control over unless the GC and owner are willing to negotiate:
1. Timelines
2. Change processes
3. Billing processes
4. Dispute resolution
And there are two things you have control over:
1. Your internal processes to properly address the contractual requirements
2. Your internal process to determine if you should even bid the project due to known issues with the client, GC, or designers. Hope is not a plan.Be realistic. If things go south, ask yourself, “Can we afford to go through the pain physically and financially?”
Think about being a builder in everything you do, not just in construction, but everything else around it. You will need to build knowledge, relationships, systems, and processes to be successful.
Let’s explore what you should be looking for in the contracts and examine where systems and processes can be used to help mitigate risk. My hope is that you can take these items and turn them into a positive impact on your company tomorrow. “Discipline Equals Freedom” – Jocko Willink. Have the discipline to review the contract documents and plan how you will handle them if challenges occur.
Know Your Timelines and Notifications: Submittals, RFIs, Delays and Response Windows
Time is one of your most valuable assets on a project. Contracts define timeframes that affect your schedule, your procurement, and your liability. Understanding the requirements and hitting those target dates can help mitigate your liability.
• Submittal timeframes: When are submittals due, and how long does the design team have to review them? Is it built into your procurement schedule?
• RFI response timeframes: Unanswered RFIs can stall work and create claims. Know how many days the contract allows for response.
• Cost notification requirements: How quickly must you notify the owner or GC? Does
• Delay notifications: When weather, late deliveries, or owner-caused impacts delay your work, does your team have the tools to track and notify in a timely manner?
• Rain day and weather procedures: Many contracts have specific requirements for how weather delays are documented and claimed. Do you have a process to track rain and mud delays?. For all the items noted above, create a calendar or task system for weekly follow-up to confirm proper dates are met.
Change Order Processes and Who can Approve/ Authorize
It is critical to understand the process for changes on the project in addition to the timelines, what format, overhead and profit allowed, time and material procedures, and force account work. There are owners and GCs that play the game to hold approval as long as possible. It’s not right, but it happens.
Do not proceed with work until there is a meeting of minds. This could be an approved change order, direction to proceed on time and material, or direction on force account. In any case, negotiate the change order, time, and payment terms for the work (especially if there is over a month of work to be performed). This can dramatically affect your cash flow.
Payment Processes
One of the most common challenges is treating payment as something that happens to you rather than something you can control. You do the work, you submit the pay app, and then you wait. Sixty days… Ninety days go by. You follow up once, maybe twice, and then you are sitting